Schedule Status - Week 3 & 4
- Project status: ON-SCHEDULE
- Expected Hours: 71 + 84 = 155
- Hours Spent: 54 + 62 = 116
- Task expected: 16 + 14 = 30
- Tasks completed = 16 + 14 = 30
- Hours Delayed: 0
- Hours in Advance: 0
- Balance: 0
Schedule Status - Week 4
- Project status: ON-SCHEDULE
- Expected Hours: 84
- Hours Spent: 51
- Hours Delayed: 0
- Hours in Advance: 0
- Balance: 0
Electronics & Structure
The electronics a structure progress can be seen in the deliverable 3 video:
https://youtu.be/eA61HoJAOE4
Vending Machine SW